The Illinois Final Waiver of Lien form is a document used in the construction industry to officially release any claims or rights to a lien by a contractor, subcontractor, or supplier against a property. This waiver is given in exchange for payment and signifies that the signer has received full compensation for all labor, services, materials, and any extras provided to the property. It's a crucial step in ensuring clear title and preventing future disputes over property ownership and payments.

Customize Form Here
Overview

In the realm of construction and property development in Illinois, navigating the legal intricacies of mechanics’ liens can be a formidable challenge for contractors, laborers, and property owners alike. Central to this navigation is the Illinois Final Waiver of Lien form, a crucial document designed to prevent potential disputes over payments by waiving any future claims against the property related to the work or materials supplied. This form serves two primary purposes: it acts as a formal acknowledgment by a contractor or subcontractor of having received payment for all labor, services, and materials provided to a property, and it relinquishes their right to file a mechanics’ lien against the property for additional compensation. By covering aspects such as the identification of the property, the owner, the scope of work provided, and the total agreed upon payment, including any extras or change orders, the form effectively clears the property of claims under Illinois' mechanics’ lien statutes. Furthermore, the contractor’s affidavit segment of the form adds a layer of protection for property owners by ensuring all parties involved in the work have been compensated and that there are no outstanding claims. Drafted with precision and conforming strictly to legal standards, this form is indispensable for maintaining the financial and legal integrity of construction projects within Illinois, safeguarding the interests of all parties involved.

Preview - Illinois Final Waiver Of Lien Form

FINAL WAIVER OF LIEN

STATE OF ILLINOIS

} SS

Gty # _____________________

COUNTY OF _____________________________

Escrow # _____________________

TO WHOM IT MAY CONCERN:

WHEREAS the undersigned has been employed by ____________________________________________________________________

to furnish _____________________________________________________________________________________________________

for the premises known as ________________________________________________________________________________________

of which ___________________________________________________________________________________________ is the owner.

THE undersigned, for and in consideration of _________________________________________________________________

($__________________________) Dollars, and other good and valuable considerations, the receipt whereof is hereby acknowledged,

do(es) hereby waive and release any and all lien or claim of, or right to, lien, under the statutes of the State of Illinois, relating to mechanics’ liens, with respect to and on said above-described premises, and the improvements thereon, and on the material, fixtures, apparatus or machinery furnished, and on the moneys, funds or other considerations due or to become due from the owner, on account of all labor, services, material, fixtures, apparatus or machinery, heretofore furnished, or which may be furnished at any time hereafter, by the undersigned for the above-described premises, INCLUDING EXTRAS.*

DATE ____________________________ COMPANY NAME ________________________________________________________

ADDRESS ________________________________________________________________

SIGNATURE AND TITLE _______________________________________________________________

* EXTRAS INLCUDE BUT ARE NOT LIMITED TO CHANGE ORDERS, BOTH ORAL AND WRITTEN, TO THE CONTRACT.

-------------------------------------------------------------------------------------------------------------------------------------------------------------------

STATE OF ILLINOIS

} SS

CONTRACTOR’S AFFIDAVIT

COUNTY OF _____________________________

TO WHOM IT MAY CONCERN:

 

 

THE UNDERSIGNED, (NAME) ____________________________________________ BEING DULY SWORN, DEPOSES

AND SAYS THAT HE OR SHE IS (POSITION) __________________________________________________________________ OF

(COMPANY NAME) _______________________________________________________________________________ WHO IS THE

CONTRACTOR FURNISHING __________________________________________________________ WORK ON THE BUILDING

LOCATED AT ________________________________________________________________________________________________

OWNED BY __________________________________________________________________________________________________

That the total amount of the contract including extras* is $______________________________ on which he or she has received

payment of $ __________________________ prior to this payment. That all waivers are true, correct and genuine and delivered

unconditionally and that there is no claim either legal or equitable to defeat the validity of said waivers. That the following are the names and addresses of all parties who have furnished material or labor, or both, for said work and all parties having contracts or sub contracts for specific portions of said work or for material entering into the construction thereof and the amount due or to become due to each, and that the items mentioned include all labor and material required to complete said work according to plans and specifications:

NAMES AND ADDRESSES

WHAT FOR

CONTRACT PRICE INCLDG EXTRAS*

AMOUNT

PAID

THIS

PAYMENT

BALANCE

DUE

TOTAL LABOR AND MATERIAL INCLUDING EXTRAS* TO COMPLETE

That there are no other contacts for said work outstanding, and that there is nothing due or to become due to any person for material, labor or other work of any kind done or to be done upon or in connection with said work other than above stated.

DATE ___________________________ SIGNATURE _______________________________________________________

SUBSCRIBED AND SWORN TO BEFORE ME THIS _______________ DAY OF ___________________________,________,

*EXTRAS INCLUDE BUT ARE NOT LIMITED TO CHANGE

ORDERS, BOTH ORAL AND WRITTEN, TO THE CONTRACT.

________________________________________________

NOTARY PUBLIC

Copyright ©2005 Greater Illinois Title Company. All Rights Reserved. http://gitc.com/forms/

Compliments of Greater Illinois Title Company; for Internal and External Use.

Universal Doc Ref: GP_IEF0029-20050804-R1-0

File Specs

Fact Number Description
1 The form is used in the State of Illinois.
2 It is designed to waive and release any lien claims under Illinois mechanics' lien statutes.
3 The waiver pertains to labor, services, materials, fixtures, apparatus, or machinery furnished.
4 It includes work already done and may cover work to be done in the future.
5 Extras, including both oral and written change orders, are covered under this waiver.
6 The form requires the company's name, address, and the signature along with the title of the signatory.
7 A contractor's affidavit is included, requiring detailed information about the contract value, payments received, and balances due.
8 It lists all parties involved in providing labor or materials, the contract prices, including extras, and the balance due to them.
9 The form must be notarized upon completion.
10 Governing laws for this form are the mechanics' lien statutes of the State of Illinois.

Detailed Instructions for Filling Out Illinois Final Waiver Of Lien

Once the work on a property in Illinois comes to completion and it's time to ensure all financial obligations have been met, a Final Waiver of Lien form plays a critical role. This document is a declaration from a contractor, subcontractor, or supplier that they have received the payment in full for all the services or materials provided and thereby waive any right to place a lien on the property for those services or materials. The process of filling out this form is straightforward but demands attention to detail to ensure all information is accurate and complete.

To correctly fill out the Illinois Final Waiver Of Lien form, follow these steps:

  1. Start by entering the County and City where the property is located at the top of the form.
  2. Fill in the Gty # and Escrow # if applicable. These are identification numbers that might be provided by your lawyer or the title company.
  3. Identify the company or individual who employed you in the space provided after "WHEREAS the undersigned has been employed by".
  4. Describe the services or materials you furnished for the project in the next blank section.
  5. Enter the address or description of the premises where the work was performed.
  6. Fill in the owner's name of the property.
  7. In the sentence that begins with "THE undersigned, for and in consideration of", enter the total dollar amount you were paid. Make sure to write the amount in both words and figures.
  8. Indicate the date when you are filling out this waiver in the space provided at the bottom.
  9. Enter the Company Name, Address, and the Signature and Title of the authorized person completing this form.
  10. If there were any extras or change orders that are not included in the original contract sum, make sure they are also mentioned and included in the total payment received.
  11. For the CONTRACTOR’S AFFIDAVIT section, start by writing the county and full name of the signee where indicated.
  12. Fill in your position in the company and the company name in the respective fields.
  13. Describe the work your company provided on the specified building and its location.
  14. Input the total amount of the contract including extras, followed by the amount received prior to this final payment.
  15. Before signing, list all parties involved in the project, what they were contracted for, their contract price including extras, the amount paid to them up to this point, and the balance due if any.
  16. Indicate the total labor and material costs, including extras, needed to complete the project.
  17. Confirm that there are no outstanding contracts or debts related to the project.
  18. Sign and date the form, then have it notarized to authenticate the affidavit.

Completing the Final Waiver of Lien form is an essential step in finalizing your role in a construction or renovation project in Illinois. It not only signifies that you have received payment in full but also legally releases any claim over the property related to the work you completed. It is crucial to review all the details carefully before submission to ensure that all information is accurate and that the waiver reflects the full scope of the work and payments received.

More About Illinois Final Waiver Of Lien

  1. What is the purpose of the Illinois Final Waiver of Lien form?

Its primary aim is to officially release any claims for payments related to mechanics' liens that contractors, subcontractors, or suppliers might have against a property once they have been fully compensated. By signing this document, the individual or company indicates they have received payment for their work, materials, or other services provided and waives their right to place a lien on the property in question. This is crucial for property owners who want to ensure that no legal claim can be placed on their property for the work stated, thereby providing peace of mind and clarity in property transactions.

  1. When should the Illinois Final Waiver of Lien form be used?

This form should be used at the completion of any project involving construction, repair, or provision of materials or equipment when all payments have been made to those who supplied labor or materials. It's a confirmation that the contractor, subcontractor, or supplier has received full payment and agrees to waive any future liens against the property. Property owners or general contractors often request this form to ensure that all financial obligations related to the project are settled, thus protecting the property from potential future encumbrances.

  1. What does the inclusion of "EXTRAS" mean in the waiver form?

"EXTRAS" refers to any additional work, materials, or amendments to the original contract that were agreed upon after the contract's initiation. This may include change orders, both oral and written, which adjust the project's scope, materials, or time frame. The inclusion of "EXTRAS" in the waiver form ensures that these additional agreed-upon tasks are covered by the waiver, indicating that the contractor has been compensated for all work performed, including any adjustments or changes made during the project's course.

  1. Is the Final Waiver of Lien form legally binding?

Yes, once signed, the Illinois Final Waiver of Lien form is legally binding. This means that the individual or company relinquishes their right to file a mechanics' lien against the property in question for the labor, services, or materials provided. For the waiver to be considered valid and enforceable, it must be executed willingly by the party receiving the payment and should accurately reflect that full compensation has been received for all work up to the date specified in the form. It's also important that the document be notarized, adding an additional layer of legal formalization.

  1. Can a party still file a lien after signing a Final Waiver of Lien?

Typically, once a Final Waiver of Lien is signed and payment has been confirmed, the party should not file a lien for the work covered under the waiver. The waiver signifies that all payments for the work described have been satisfactorily received. Filing a lien after issuing a waiver could result in legal challenges and may be considered fraudulent if it pertains to the work and payments already covered by the waiver. However, if there are disputes over additional work not included in the final waiver, it might be a different scenario requiring separate legal advice.

  1. Are there any steps that should be taken after the Final Waiver of Lien is received?

After receiving a Final Waiver of Lien, it is highly recommended that the property owner or the party responsible keeps the document securely as part of the property's official records. This action serves as proof that all dues to contractors, subcontractors, or suppliers have been paid and that the property is free from potential liens related to the work completed. Additionally, consulting a legal professional to ensure that all other potential legal obligations are met and that the property's title is clear can provide extra protection and peace of mind.

Common mistakes

One common mistake when filling out the Illinois Final Waiver Of Lien form relates to not fully understanding the gravity of the document. This form effectively removes the right to file a lien against the property for the services or materials provided, assuming that payment has been made. Unfortunately, some people rush through this process without ensuring the payment reflects accurately in the consideration section. It's crucial that the amount stated as received in the waiver matches the actual payments. Incorrectly reporting this figure can lead to disputes and potential legal woes, especially if the amount declared does not cover all claims for labor and materials provided.

Another error involves the identification details of the parties and the property. The form requires specific information, including the proper names of the property owner, the contracting party, and the precise address of the premises under consideration. Mistakes or inaccuracies in these details can invalidate the waiver, potentially leaving a party without its intended legal protection. Accuracy is paramount; overlooking the details, misspelling names, or providing incomplete addresses can complicate matters, especially if a dispute arises down the line regarding the scope or fulfillment of the agreement.

Furthermore, a significant oversight occurs when individuals neglect to fully account for and list "extras" as defined in the waiver. Extras can include any additional work or materials that were not initially part of the primary contract but were later deemed necessary. Failing to account for these extras in the waiver means they are not covered by the release of lien, leaving an opening for potential liens regarding these supplementary services or materials. It's critical to carefully review and include all extra work or materials in the waiver to ensure a comprehensive release of claims.

Lastly, the procedural step of notarization often becomes a stumbling block. The form mandates that the waiver be subscribed and sworn before a notary public, providing a layer of legal validity and protection. Sometimes, individuals overlook this requirement or incorrectly assume it's a mere formality. This misstep can severely undermine the document's enforceability and credibility. Completing the notarization process diligently confirms that the signatory's identity has been verified and that they indeed signed the document willingly, greatly reducing the risk of future disputes over the waiver's legitimacy.

Documents used along the form

When it comes to managing construction projects or real estate developments in Illinois, the Final Waiver of Lien form is just one crucial piece of documentation needed to ensure legal compliance and protect all parties involved. This document essentially signifies that a contractor or supplier has been fully paid and waives their right to place a lien on the property for amounts owed. However, this form often works in tandem with other essential documents to provide a comprehensive legal framework. Here's an overview of six other forms and documents frequently used in conjunction with the Illinois Final Waiver of Lien form.

  • Preliminary Notice: A document sent to the property owner and general contractor at the beginning of a project, which notifies them of the sender's rights and intentions to file a lien if unpaid. This notice helps protect those rights in many states.
  • Notice of Intent to Lien: Issued as a warning to the property owner and other stakeholders that the issuer intends to file a lien on the property unless payment is made. This is often a required step before filing an actual lien.
  • Mechanic’s Lien: A legal claim against a property by a contractor, subcontractor, or supplier who has not received payment for work performed or materials supplied. This document is filed with the county recorder's office.
  • Partial Waiver of Lien: Similar to the Final Waiver of Lien, this document waives the signer's right to file a lien to the extent of the payment received. It is typically used for partial payments throughout the project.
  • Contractor’s Affidavit: A sworn statement by the contractor that outlines the work performed, the materials supplied, the costs, and the status of the payments. It usually includes a list of all subcontractors and suppliers involved in the project.
  • Release of Lien: Issued once a lien has been satisfied or a misunderstanding has been cleared, this document removes the lien from the property's record, thus eliminating any encumbrance on the title.

Together, these documents form a network of legal safeguards that ensure transparency, honesty, and fairness in construction and real estate transactions. By meticulously managing these forms, property owners, contractors, and other stakeholders can help prevent disputes and ensure smooth project progression. Each document serves a specific purpose, providing clarity and security at different stages of a project, and ensuring that everyone's rights are protected and obligations are clear.

Similar forms

The Illinois Final Waiver of Lien form is a crucial document used in construction and remodeling projects to ensure that contractors and suppliers officially renounce any right to place a lien on a property once they have been paid. This form, specific to the legal landscape of Illinois, shares similarities with other legal documents designed to protect parties in various transactions. Below are four documents that are related to the Illinois Final Waiver of Lien in function and purpose:

  • Partial Waiver of Lien: Similar to the Final Waiver of Lien, a Partial Waiver of Lien is used during the course of a construction project, often after each payment installment. While the Final Waiver signifies the completion of payment and work under the contract, the Partial Waiver serves as an interim step, relinquishing lien rights up to the amount paid to date, without covering the entirety of the project scope.

  • Mechanic's Lien: This is a legal claim against a property that has been remodeled or improved. It's akin to the opposite of a lien waiver. Where the Final Waiver of Lien releases the property from claims, a Mechanic's Lien is a contractor’s, supplier’s, or laborer’s legal recourse to secure payment they have not received for services rendered. It creates a financial encumbrance on the property’s title, making it difficult to sell or refinance until the lien is settled.

  • Release of Mechanic's Lien: This document comes into play after a Mechanic's Lien has been filed. It officially documents the settlement of the outstanding debt or dispute that prompted the lien. Once the owed party receives payment, the Release of Mechanic's Lien clears the property’s title of the lien, similarly restoring free and clear status to the property as does the Final Waiver of Lien.

  • Contractor’s Affidavit: Also known within the Illinois Final Waiver of Lien form, a Contractor's Affidavit is a declaration that all services, labor, and materials provided up to a certain point have been duly compensated, and it lists all sub-contractors and suppliers involved along with the status of their payments. It’s often used in conjunction with lien waivers to provide transparency and assurance to property owners that no outstanding debts will lead to a lien on their property.

Each of these documents plays a vital role in managing and mitigating financial and legal risks in real estate transactions and construction projects, ensuring that all parties are protected and aware of their rights and responsibilities.

Dos and Don'ts

When completing the Illinois Final Waiver of Lien form, understanding and adhering to proper guidelines can streamline the process and prevent legal discrepancies. Below are five dos and don'ts that should be followed:

Do:

  • Ensure all the information provided is accurate and matches the details of the project and agreement, including the full legal name of the property owner, your company details, and the description of the services or materials provided.
  • Include the exact amount that has been paid to you for your services or materials, along with any unpaid extras or change orders as agreed upon in the contract.
  • Sign and date the form in the presence of a notary public to validate its authenticity. This formal acknowledgment is crucial for the document's legal standing.
  • Keep a copy of the completed and notarized waiver for your records. This document is important for resolving any future disputes regarding payments or lien rights.
  • Ensure that the form is filled out entirely before submission. Incomplete forms can cause delays or be considered invalid, complicating the waiver process.

Don't:

  • Do not leave any sections of the form blank. If a section doesn't apply to your situation, mark it as "N/A" (not applicable) to indicate that you did not overlook it.
  • Avoid rounding off figures. Provide exact amounts to maintain accuracy and transparency in the financial transactions being waived.
  • Do not sign the waiver before all the work is completed unless it specifically relates to a partial payment for completed portions of the work. Signing off too early can forfeit your right to claim payments for any remaining tasks.
  • Do not forget to list all extras, including oral and written change orders, to ensure all aspects of the work and associated costs are covered by the waiver.
  • Avoid notarizing the document before thorough review and ensuring everything is in order. Once notarized, changes are more challenging and require issuing a new waiver.

Misconceptions

Understanding the Illinois Final Waiver of Lien requires clarity about what it entails, as misconceptions can lead to misuse of this important document. Here are eight common misconceptions about the Illinois Final Waiver of Lien form.

  • It's only necessary for large projects: One common misconception is that the Final Waiver of Lien form is only necessary for large construction projects. In reality, it's important for projects of all sizes to ensure that all financial obligations for labor, services, materials, and equipment have been fulfilled.

  • It relinquishes all future claims automatically: Some believe that signing this waiver means they cannot make any future claims related to the project. However, the form specifically waives rights to liens for the work already completed and paid for, not for future work or unresolved disputes unless specified.

  • Signing it immediately releases funds: Another misconception is that the waiver immediately releases due payments. The truth is, while it's a step towards payment, processes between financial institutions and parties may delay the actual release of funds.

  • No need for notarization: People often think notarizing the form isn’t necessary. Yet, the presence of a notary public section underlines the importance of notarization to affirm the signer’s identity and prevent fraud.

  • It covers only the signatory’s interests: There's a belief that the waiver only concerns the party signing it. However, it should also detail other parties involved in the project, including subcontractors and material suppliers, ensuring they've been paid or will be paid.

  • Extras are automatically included: Many assume "extras" or change orders are automatically covered by the waiver. The form does note that extras are included, but specifics should be clearly detailed to prevent future disputes.

  • It can be signed at any project stage: Some think this form can be signed at any stage of the project. It is specifically a final waiver, meaning it's meant to be signed towards the project's conclusion, confirming the settlement of all accounts.

  • It's binding without the owner’s signature: A common misunderstanding is that the document is binding without the property owner's signature. In reality, the form serves as an agreement between the contractor (or subcontractor) and the owner, acknowledging that payment has been made and received.

Understanding these misconceptions about the Illinois Final Waiver of Lien form can help ensure that it is appropriately used and interpreted. This promotes fairness and transparency in settling financial obligations related to construction projects.

Key takeaways

Understanding the process of completing and utilizing the Illinois Final Waiver of Lien form is essential for ensuring a smooth closure to construction projects. This form serves as an official release of any claim for payment that a contractor, subcontractor, supplier, or laborer might otherwise have against a property due to materials or labor provided. Below are seven key takeaways to help guide you through the process:

  • Proper Identification: It's crucial to accurately fill out the county, city, escrow number (if applicable), and other identification fields at the beginning of the form to ensure its validity.
  • Clear Statement of Work: The form requires a detailed description of the services or materials provided. This includes the type of work done, the materials supplied, and any extras or changes to the original contract.
  • Complete Details of Payment: The amount acknowledged in the waiver must reflect the total compensation received for the work, including any extras or adjustments made to the contract after the work began. This helps to prevent disputes over payment amounts.
  • Inclusion of Extras: Extras, including both oral and written change orders to the contract, must be clearly indicated. This ensures that any additional work or materials provided after the initial agreement are also waived from future lien claims against the property.
  • Accurate Contractor Information: The waiver requires the contractor’s complete and accurate information, including the company name, address, and the signature and title of the signing party. This information is vital for legal and record-keeping purposes.
  • Contractor’s Affidavit: Alongside the waiver, there's a contractor's affidavit section. This part attests to the total amount of the contract, payments received, and the validity of waivers. It also requires listing all parties involved and the amounts paid or due, cementing the comprehensiveness of the waiver.
  • Notarization: To finalize the waiver and affidavit's authenticity and enforceability, they must be signed in the presence of a notary public. The notarization process adds a layer of legal security, certifying that the signee is indeed who they claim to be.

Filling out the Illinois Final Waiver of Lien form correctly and comprehensively is a step towards ensuring all parties involved in a construction project are satisfied, and the property is cleared of any possible lien claims. This process not only maintains professionalism but also fortifies trust and transparency among parties, ultimately leading to a smoother project conclusion.